04/06/2011 - Tiles Completed
01/06/2011 - Kitchen Completed
31/05/2011 - Caesar Stone & Sink Installed
27/05/2011 - Entry Door installed, Garage Door Installed
26/05/2011 - Internal Doors installed
23/05/2011 - Tiling Started
20/05/2011 - Kitchen Cabinate Completed, Island installed
13/05/2011 - Waterproofing Completed, Powder Room, Bathroom, Laundry and Ensuite Cabinate Completed
06/05/2011 - Stairs Completed
05/05/2011 - Gyprocking Completed
29/04/2011 - Gyprocking started
28/04/2011 - Insulation Completed
27/04/2011 - Down Pipes Installed
21/04/2011 - Electrical Completed
20/04/2011 - Bi-fold Door and Balcony door installed
15/04/2011 - Scaffolding Removed
14/04/2011 - Cladding Completed
06/04/2011 - Cladding Started
05/04/2011 - Bricks Cleaned
02/04/2011 - Bricks Completed
16/03/2011 - Roof Completed, Fascia and Guttering Completed
28/02/2011 - Bricks Started
18/02/2011 - Framing & Plumbing Completed
18/12/2010 - Slab Poured
11/11/2010 - Council Approval
25/10/2010 - Internal Colour selection
21/09/2010 - Plan lodged in Council
15/09/2010 - Developer Approval
27/7/2010 - External Colours selection
27/7/2010 - Building Contract Signed
26/7/2010 - Landscape Plan received
28/6/2010 - Metricon Tender Acceptance
13/5/2010 - Land settled
18/4/2010 - Deposit paid to Metricon
8/3/2010 - Deposit placed on Block of land