Build Dates

04/06/2011 - Tiles Completed

01/06/2011 - Kitchen Completed

31/05/2011 - Caesar Stone & Sink Installed

27/05/2011 - Entry Door installed, Garage Door Installed

26/05/2011 - Internal Doors installed

23/05/2011 - Tiling Started

20/05/2011 - Kitchen Cabinate Completed, Island installed

13/05/2011 - Waterproofing Completed, Powder Room, Bathroom, Laundry and Ensuite Cabinate Completed

06/05/2011 - Stairs Completed

05/05/2011 - Gyprocking Completed

29/04/2011 - Gyprocking started

28/04/2011 - Insulation Completed

27/04/2011 - Down Pipes Installed

21/04/2011 - Electrical Completed

20/04/2011 - Bi-fold Door and Balcony door installed

15/04/2011 - Scaffolding Removed

14/04/2011 - Cladding Completed

06/04/2011 - Cladding Started

05/04/2011 - Bricks Cleaned

02/04/2011 - Bricks Completed

16/03/2011 - Roof Completed, Fascia and Guttering Completed

28/02/2011 - Bricks Started

18/02/2011 - Framing & Plumbing Completed

18/12/2010 - Slab Poured

11/11/2010 - Council Approval

25/10/2010 - Internal Colour selection

21/09/2010 - Plan lodged in Council

15/09/2010 - Developer Approval

27/7/2010 - External Colours selection

27/7/2010 - Building Contract Signed

26/7/2010 - Landscape Plan received

28/6/2010 - Metricon Tender Acceptance

13/5/2010 - Land settled

18/4/2010 - Deposit paid to Metricon
 
8/3/2010 - Deposit placed on Block of land